Title: Approve a resolution finding the use of Construction Manager-at-Risk method as authorized by Subchapter F, Chapter 2269 of the Texas Government Code, is the project delivery method that provides the best value to the City for construction of the Colony Park and Givens Pools. (Note: MBE/WBE goals will be established prior to issuance of this solicitation.)
Attachments: 1. Draft Resolution, 2. Recommendation for Action, 3. Recommendation for Action
Date Action ByActionAction DetailsMeeting Details
No records to display.
Posting Language
Title
Approve a resolution finding the use of Construction Manager-at-Risk method as authorized by Subchapter F, Chapter 2269 of the Texas Government Code, is the project delivery method that provides the best value to the City for construction of the Colony Park and Givens Pools.

(Note: MBE/WBE goals will be established prior to issuance of this solicitation.)

Body
Lead Department
Capital Contracting Office

Managing Department(s)
Capital Contracting Office

Fiscal Note
A Recommendation for Council Action with the not to exceed contract amount for the resultant contract will be presented to Council once the Construction Manager-at-Risk selection has been completed.

Purchasing Language:
This request is for Council to authorize the use of the Construction Manager-at-Risk; therefore, no solicitation has yet been initiated.

For More Information:
Inquiries should be directed to the City Manager's Agenda Office, at 512-974-2991 or AgendaOffice@austintexas.gov.

NOTE: Respondents to this solicitation, and their representatives, shall direct inquiries to Rolando Fernandez, 512-974-7749 or Beverly Mendez, 512-974-9423.

Additional Backup Information:
State Statute governs construction procurement for municipalities. The standard method of contracting used for construction services is competitive bidding where the contract is awarded to the lowest responsible bidder. Texas Government Code Chapter 2269 allows for methodologies alternate to low bidding method which may provide the best value to the municipality. These alternate methodologies include: Competitive Sealed proposals, Construction Manager-at-Risk (CMAR), Design-Build, and Job Order Contracting. Texas Local Government Code Section 252.022(d) allows the City to adopt and use an alternative method such as CMAR under Chapter 2269 of the Texas Government Code if such a method provides a better value for the City.


The CMAR method is a project delivery method where the City will contrac...