File #: 25-2404   
Type: Consent Status: Agenda Ready
File created: 11/4/2025 In control: City Council
On agenda: 12/11/2025 Final action:
Title: Authorize a contract for construction services for the Walnut Creek - Thompkins Tributary at Lavina Lane Stream Stabilization Project for Austin Watershed Protection with Austin Filter Systems, Inc., in the amount of $1,162,813, plus a $116,282 contingency, for a total contract amount not to exceed $1,279,095. Funding: $1,279,095 is available in the Capital Budget of Austin Watershed Protection.
Indexes: District 1
Attachments: 1. MWBE Summary, 2. Map, 3. Recommendation for Action
Date Action ByActionAction DetailsMeeting Details
No records to display.

Posting Language
Title

Authorize a contract for construction services for the Walnut Creek - Thompkins Tributary at Lavina Lane Stream Stabilization Project for Austin Watershed Protection with Austin Filter Systems, Inc., in the amount of $1,162,813, plus a $116,282 contingency, for a total contract amount not to exceed $1,279,095. Funding: $1,279,095 is available in the Capital Budget of Austin Watershed Protection.

 

Body

Lead Department

Austin Financial Services.

 

Managing Department
Austin Capital Delivery Services.

 

Fiscal Note

Funding is available in the Capital Budget of Austin Watershed Protection.

 

Procurement Language:

Austin Financial Services issued an Invitation for Bids IFB 6100 CLMC1113 for these services. The solicitation published on June 30, 2025, and closed on August 21, 2025. Of the five bids received, the bid submitted by the recommended contractor was the lowest responsive bid received. A complete solicitation package, including a tabulation of the bids received, is available for viewing on the City’s website. This information can currently be found at https://financeonline.austintexas.gov/afo/account_services/solicitation/solicitation_details.cfm?sid=142485.

 

MBE/WBE:

This contract will be awarded in compliance with City Code Chapter 2-9A (Minority-Owned and Women-Owned Business Enterprise Procurement Program) by meeting the goals with 16.80% MBE and 5.03% WBE participation.

 

For More Information:

Direct questions regarding this Recommendation for Council Action to the Austin Financial Services - Central Procurement at FSDCentralProcurementRCAs@austintexas.gov or 512-974-2500. Respondents to the solicitation and their Agents should direct all questions to the Authorized Contact Person identified in the solicitation.

 

Additional Backup Information:

Ongoing channel incision has created steep and unstable stream banks between single-family homes. This project aims to stabilize approximately 750 feet of stream bank. The channel bed has steep vertical drops which indicate instability and further erosion if the reach is not actively stabilized. Erosion threatens private property, public utilities, and infrastructure. The stream reach is ranked in the top 20 priority reaches citywide for erosion hazard.

 

The project consists of erosion protection measures which includes grading, replacement of a drainage outfall, and native landscaping using shade trees, ornamental trees, and grasses. 

 

This item includes two allowances of $30,000 to be used to address replacement of three existing sheds and an allowance of $10,000 to be used to address replacement of an existing deck. An allowance is an amount that is specified and included in the construction contract or specifications for certain items of work when details are not determined at the time of bidding.

 

Due to the potential for unknown subsurface conditions, a 10% contingency in funding has been included to allow for the expeditious processing of any change orders to cover any unforeseen construction costs associated with the project. By authorizing the additional contingency funding, Council is authorizing any change orders within the contingency amount.

 

The project will include traffic control measures at the construction entrance along Thompkins Drive while maintaining normal traffic flow with little impact to residents. 

 

Delay in the approval of this construction contract will continue to increase the risk of damage to adjacent residential properties. 

 

The contract allows 180 calendar days for completion of this project. 

 

This project is located within zip code 78753 (District 1).