Posting Language
Title
Authorize an amendment to the contract for professional design services, for the Barton Springs Road Bridge Over Barton Creek Project, for Austin Transportation and Public Works with URS Corporation in the amount of $4,000,000, for a revised total contract amount not to exceed $15,863,005. Funding: $4,000,000 is available in the Capital Budget of Austin Transportation and Public Works.
Body
Lead Department
Austin Financial Services.
Managing Department
Austin Capital Delivery Services.
Fiscal Note
Funding is available in the Capital Budget of Austin Transportation and Public Works.
Procurement Language:
Contract Amendment.
MBE / WBE:
This contract was awarded in compliance with the City Code 2-9A (Minority-Owned and Women-Owned Business Enterprise Procurement Program). Current participation to date is 6.49% MBE and 6.86% WBE.
Prior Council Action:
April 24, 2025 - Council accepted and appropriated $32M in Bridge Investment Program grant funds for replacement, Item 50, on an 11-0 vote.
May 2, 2024 - Council approved an amendment to the professional services agreement with URS Corporation for the Barton Springs Road Bridge Over Barton Creek, Item 16, on an 11-0 vote.
December 14, 2023 - Council conducted a public hearing and approved the recommended alternative in the Preliminary Engineering Report to replace the Barton Springs Road Bridge over Barton Creek.
October 21, 2021 - Council approved an amendment to the professional services agreement with URS Corporation for the Barton Springs Road Bridge Over Barton Creek, Item 4, on an 11-0 vote.
August 3, 2017 - Council approved an amendment to the professional services agreement with URS Corporation for the Barton Springs Road Bridge Over Barton Creek, Item 4, on an 11-0 vote.
May 21, 2015 - Council approved a professional services agreement with URS Corporation for the Barton Springs Road Bridge Over Barton Creek, Item 35, on a 9-0 vote.
For More Information:
Direct questions regarding this Recommendation for Council Action to the Austin Financial Services - Central Procurement at: FSDCentralProcurementRCAs@austintexas.gov or 512-974-2500.
Additional Backup Information:
The Barton Springs Road Bridge is located near the intersection of Barton Springs Road and Azie Morton Road. Originally constructed in 1925 and widened in 1946, the bridge provides a critical transportation connection between MoPac, downtown Austin, and the South Lamar and South Congress corridors. It accommodates vehicular, bicycle, and pedestrian traffic and serves as a primary northern access point to the Zilker and Barton Hills neighborhoods via Azie Morton Road.
Council approved the replacement of the existing three-span bridge with a new bridge featuring Y-shaped piers oriented parallel to the creek. Selected from five alternatives evaluated during preliminary engineering, the approved concept maximizes visual openness beneath the bridge while improving the experience for pedestrians and paddlers. The design also provides additional space for the Zilker Eagle Train and the Ann and Roy Butler Hike-and-Bike Trail. Currently, the bridge’s roadway alignment shifts at the intersection with Azie Morton Road, creating operational challenges. Replacing the bridge will improve design, mobility and safety for all transportation modes, and enhance access for surrounding neighborhoods, local businesses, Zilker Park visitors, and special event attendees.
The request authorizes additional professional services necessary to complete the National Environmental Policy Act (NEPA) process, final design, bid, award, and construction phase services. Completion and acceptance of the NEPA process are required before the federal Bridge Investment Program (BIP) Grant Agreement can be executed.
The NEPA requirements have extended the anticipated project schedule by approximately two years. However, the BIP grant provides the funding necessary to advance the project into construction. The remaining design and environmental work includes field investigations, coordination with state and local historic preservation authorities, and stakeholder and public engagement. Austin Capital Delivery Services will coordinate and communicate to the public any field investigations that may require temporary lane closures that could impact traffic.
AUTHORIZATION HISTORY
|
AMOUNT |
DATE |
DESCRIPTION |
|
$300,00.00 |
05/21/2015 |
(Council) - Professional Engineering Services for Barton Springs Road Bridge Over Barton Creek Project |
|
$692,387.00 |
08/03/2017 |
(Council) - Preliminary Phase Services |
|
$1,813,618.00 |
10/21/21 |
(Council) - Final Preliminary Phase Services |
|
$9,000,000.00 |
05/02/2024 |
(Council) - Design Phase Services |
|
$4,000,000.00 |
12/03/2026 |
Proposed (Council) - Additional authority for final design, NEPA, bid award, construction phase services |
|
$15,806,005.00 |
Total Contract Authorization |
|
|
|
|
CONTRACT HISTORY
|
AMOUNT |
DATE |
DESCRIPTION |
|
$299,543.55 |
05/21/2015 |
Professional Engineering Services for Barton Springs Road Bridge Over Barton Creek Project |
|
$692,387.00 |
08/03/2017 |
SA #1 - Additional Preliminary Phase Services for concept and bridge selection |
|
$1,706,591.00 |
10/21/2021 |
SA #2 - Additional Preliminary Phase Services for completion of concept and confirmation processes |
|
$35,244.43 |
02/25/2022 |
SA #3 - Additional Preliminary Phase Services for environmental investigations |
|
$59,718.36 |
02/07/2024 |
SA #4 - Final Preliminary Phase Services |
|
$8,571,710.32 |
06/25/2024 |
SA #5 - Design Phase Services |
|
$1,250,180.47 |
Proposed |
SA #6 - Final Design Phase Services and NEPA |
|
$12,615,375.13 |
Total Contract History |
.