Legislation Details

File #: 26-1698   
Type: Consent Status: Agenda Ready
File created: 4/20/2026 In control: City Council
On agenda: 5/28/2026 Final action:
Title: Authorize additional contingency for the construction contract for the Northwest Lift Station Improvements: Rock Harbor Force Main and Four Points #2 Project for Austin Water with Santa Clara Construction, LTD, to increase the amount by $537,225, for a total contract amount not to exceed $5,280,171. Funding: $537,225 is available in the Capital Budget of Austin Water.
Indexes: District 10
Attachments: 1. Map, 2. Recommendation for Action, 3. WWWC Recommendation
Date Action ByActionAction DetailsMeeting Details
No records to display.

Posting Language
Title

Authorize additional contingency for the construction contract for the Northwest Lift Station Improvements: Rock Harbor Force Main and Four Points #2 Project for Austin Water with Santa Clara Construction, LTD, to increase the amount by $537,225, for a total contract amount not to exceed $5,280,171. Funding: $537,225 is available in the Capital Budget of Austin Water.

 

Body

Lead Department

Austin Financial Services.

 

Managing Department
Austin Capital Delivery Services.

 

Fiscal Note

Funding is available in the Capital Budget of Austin Water.

 

Procurement Language:

Additional Authorization.

 

MBE / WBE:

This contract was awarded in compliance with the City Code Chapter 2-9A (Minority-Owned Business Enterprise and Women-Owned Business Enterprise Procurement Program). Current participation is 40.68% MBE and 2.09% WBE.

 

Prior Council Action:

February 13, 2025 - Council approved a contract with Santa Clara Construction LTD for NWLS Improvements: Rock Harbour Force Main and Four Points #2.

 

For More Information:

Direct questions regarding this Recommendation for Council Action to the Austin Financial Services - Central Procurement at FSDCentralProcurementRCAs@austintexas.gov or 512-974-2500.

 

Council Committee, Boards and Commission Action:

May 20, 2026 - To be reviewed by the Water and Wastewater Committee.

 

Additional Backup Information:

The Rock Harbour Force Main project consists of approximately 4,500 linear feet of a new High-Density Polyethylene force main installed from Rock Harbour Lift Station to the existing ductile iron force main on Vista Parke Drive. The alignment parallels Rock Harbour Drive, crosses FM 620, parallels Wilson Park Avenue, turns south on Woodbay Parke Drive, then connects to the existing Four Points #2 16-inch force main. The proposed force main across RM 620 will be installed via trenchless construction while the remaining force main will be open cut. There will also be 100 linear feet of ductile iron force main installed via open-cut across Wilson Parke Avenue at 12132 1/2 Wilson Parke Avenue. Also included is the demolition of Four Points #2 Lift Station and abandonment of 2,540 linear feet of gravity main and associated manholes. Lastly, the project includes the installation of the final fourth pump at the Rock Harbour Lift Station and changing the impellers on the existing three pumps.

 

At the beginning of construction, Right of Way Management identified safety gaps in the approved Traffic Control Plan. The gaps required significant plan redesign that has increased the cost and scope of the Traffic Control Plan. Additionally, the lift station and force main was previously built and maintained by the Northwest Austin Municipal Utility District #1. During construction discrepancies between the as-built drawings and actual below ground field conditions were discovered, resulting in redesign and Traffic control plan changes.

 

This additional contingency funding will allow for the expeditious processing of any change orders necessary due to conditions that were unforeseen at the time of bidding and presented later during construction. A contingency is an additional amount of money added to the construction budget to cover unforeseen construction costs associated with the project. By authorizing the additional contingency funding, Council is authorizing any change orders within the contingency amount.

 

There will be continued lane closures in this area since much of the work is located in the right-of-way. There are signs and barricades to guide the traveling public. 

 

This project is located within zip code 78726 (District 10).

 

 

AUTHORIZATION HISTORY

 

AMOUNT

DATE

DESCRIPTION

$4,224,496.50

02/13/2025

(Council) - NLSW: Rock Harbor Force Main and Four Points #2 project

$442,449.65

02/13/2025

(Council) - 10 % Contingency

$76,000.00

02/13/2025

(Administrative Authority) - NLSW: Rock Harbor Force Main and Four Points #2 

$537,224.84

05/28/2026

Proposed (Council) - Additional Contingency

$5,280,170.99

Total Contract Authorization

 

CONTRACT HISTORY

 

AMOUNT

DATE

DESCRIPTION (CO%/CUMULATIVE CO%)

$4,224,496.50

02/13/2025

Northwest Lift Station Improvements: Rock Harbour Force Main and Four Points #2 

$27,644.00

09/08/2025

Change Order # 1 - Traffic Control Phase 5 (.65%/.65%)

$89,375.00

10/30/2025

Change Order # 2 - Boring under utilities (2.12%/2.77%)

$52,808.50

12/23/2025

Change Order # 3 - Traffic Control Phase 4 (1.25%/4.02%)

$96,005.00

02/03/2026

Change Order # 4 - Traffic Control Phase 1, 2B, 3 (2.27%/6.29%)

$22,946.10

02/12/2026

Change Order # 5 - Cave and Void Mitigation (.54%/6.84%)

$90,593.98

03/11/2026

Change Order # 6 - Traffic Control Phase 5b and 6 (2.14%/8.98%) 

$537,224.84

Proposed

Council - CO#7 and additional contingency

$5,141,093.92

Total Contract History