Title: Authorize execution of a contact for construction services for the Williamson Creek Phase 1- Brassiewood Drive and Creekwood Drive Bypass Storm Drain Improvement project with Cash Construction Company, Inc., in the amount of $2,253,322, plus a $225,332 contingency, for a total contract amount not to exceed $2,478,654. [Note: This contract will be awarded in compliance with City Code Chapter 2-9A (Minority-Owned and Women-Owned Business Enterprise Procurement Program) through achievements of Good Faith Efforts with 6.62% MBE and 0.17% WBE participation].
Indexes: District 2
Attachments: 1. MWBE Summary, 2. Map, 3. Recommendation for Action
Date Action ByActionAction DetailsMeeting Details
No records to display.

Posting Language
Title

Authorize execution of a contact for construction services for the Williamson Creek Phase 1- Brassiewood Drive and Creekwood Drive Bypass Storm Drain Improvement project with Cash Construction Company, Inc., in the amount of $2,253,322, plus a $225,332 contingency, for a total contract amount not to exceed $2,478,654.  

 

[Note: This contract will be awarded in compliance with City Code Chapter 2-9A (Minority-Owned and Women-Owned Business Enterprise Procurement Program) through achievements of Good Faith Efforts with 6.62% MBE and 0.17% WBE participation].

 

Body

Lead Department

Financial Services Department.

 

Managing Department
Capital Delivery Services.

 

Amount and Source of Funding

Funding is available in the Capital Budget of the Watershed Protection Department.

 

Purchasing Language:

The Financial Services Department issued an Invitation for Bids (IFB) 6100 CLMC1016 for these services. The solicitation was issued on February 26, 2024, and closed on April 11, 2024. Of the seven offers received, the recommended contractor submitted the lowest responsive offer. A complete solicitation package, including a tabulation of the bids received, is available for viewing on the City’s Financial Services website, Austin Finance Online. This information can currently be found at: https://financeonline.austintexas.gov/afo/account_services/solicitation/solicitation_details.cfm?sid=139685.

 

For More Information:

Direct questions regarding this RCA to the Financial Services Department - Central Procurement at FSDcentralProcurementRCAs@austintexas.gov <mailto:FSDcentralProcurementRCAs@austintexas.gov> or 512-974-2500. Respondents to the solicitation and their Agents should direct all questions to the Authorized Contact Person identified in the solicitation.

 

Additional Backup Information:

This project will upgrade drainage infrastructure in the Dove Springs neighborhood, which has experienced many flooding events over the years. Homes adjacent to the Brassiewood Detention Pond at the intersection of Brassiewood Drive and South Pleasant Valley Drive have been particularly impacted by flooding due to the undersized detention pond.

 

The work consists of approximately 1,600 linear feet of new storm drain and 1,200 linear feet of associated water and wastewater reconstruction to accommodate the new storm drain.

 

Due to the potential for unknown subsurface conditions, a 10% contingency in funding has been included to allow for the expeditious processing of any change orders.  A contingency is an additional amount of money added to the construction budget to cover any unforeseen construction costs associated with the project. By authorizing the additional contingency funding, Council is authorizing any change orders within the contingency amount.

 

The project proposes lane closures and detours. The contractor will work to ensure that residents and businesses always have access to their driveways. If access cannot be maintained, written notice of limited access will be provided to the affected property owner(s) at least 24 hours in advance.

 

A delay in contract approval will impact the City’s ability to reduce flood risks for residents in the Dove Springs neighborhood.

 

The contract allows 180 calendar days for substantial completion of this project.

 

This project is located within zip code 78744 (District 2).