Title: Authorize an amendment to the design-build contract for design and construction services for the Fire and EMS Stations Rebuild and Renovations project with Flintco LLC, to increase the contract amount by $750,000 for a revised total contract amount not to exceed $27,450,000. [Note: This amendment will be awarded in compliance with City Code 2-9A (Minority Owned and Women Owned Business Enterprise Procurement Program). Current participation to date is 18.95% MBE and 1.71% WBE. Related to Items #18 and #43.
Indexes: District 3, District 9
Attachments: 1. MWBE Summary, 2. Authorization History, 3. Recommendation for Action
Date Action ByActionAction DetailsMeeting Details
No records to display.

Posting Language
Title

Authorize an amendment to the design-build contract for design and construction services for the Fire and EMS Stations Rebuild and Renovations project with Flintco LLC, to increase the contract amount by $750,000 for a revised total contract amount not to exceed $27,450,000. 

 

[Note: This amendment will be awarded in compliance with City Code 2-9A (Minority Owned and Women Owned Business Enterprise Procurement Program). Current participation to date is 18.95% MBE and 1.71% WBE. Related to Items #18 and #43.

 

Body

Lead Department

Financial Services Department.

 

Managing Department
Capital Delivery Services.

 

Fiscal Note

Funding is available through the Capital Budget of the Austin Fire Department.

 

Purchasing Language:

Contract Amendment.

 

Prior Council Action:

June 16, 2022 - Council approved an amendment to the design-build contract for the Fire and EMS Stations Rebuild and Renovations project with Flintco, LLC.

 

November 14, 2019 - Council approved a design-build contract for the Fire and EMS Stations Rebuild and Renovations project with Flintco, LLC.

 

May 9, 2019 - Council approved the use of Design Builder alternative delivery procurement method for the Fire and EMS Stations Rebuild and Renovations project.

 

For More Information:

Direct questions regarding this Recommendation for Council Action to the Financial Services Department - Central Procurement at: FSDCentralProcurementRCAs@austintexas.gov or 512-974-2500. Respondents to the solicitation and their Agents should direct all questions to the Authorized Contact Person identified in the solicitation.

 

Additional Backup Information:

The Fire and EMS Stations Rebuild and Renovations project is an effort to provide urgent repairs and upgrades to two existing Fire/EMS stations, as well as the redesign and rebuild of Fire Station 22/EMS Station 12. Facilities undergoing these upgrades are:

 

                     Fire Station 1/EMS Station 6 - In construction, estimated completion May 2024

                     Fire Station 22/EMS Station 12 - In construction, estimated completion May 2024

                     Fire Station 3 - Substantial completion, in use by Fire personnel.

 

Additional authorization is needed to complete urgent repairs, upgrades and renovations to Fire Station 1/EMS Station 12 and Fire Station 22/EMS Station 12. The two fire stations are currently in construction and are on track to be completed in May 2024.

 

Due to the age of the stations, available building records did not capture all the existing conditions accurately. Unforeseen field and utility conditions, as well as necessary infrastructure modifications, were discovered during the demolition phase. Excavation uncovered conflicting field conditions such as proximity to other utility lines, drain slope, and removed sewer lines. Additional site and building permit corrections were required to rectify the field conditions. This additional funding is necessary to complete the ongoing field modifications necessary for the project to meet building and site permitting code requirements.

 

This amendment has been approved by the City’s Change Control Committee. The Change Control Committee was established to comply with Council Resolution No. 20120126-048, which required the establishment of consistent criteria and process to evaluate contractual changes for all contracts administered by the Financial Services Department, Capital Contracting. The Change Control Committee is comprised of management-level subject matter experts.

 

A delay in approving this amendment will adversely impact the current schedule for construction. Completion is scheduled for May 2024. 

 

This project is located within zip codes 78701, 78741, and 78705 (Districts 9 and 3).