Legislation Details

File #: 26-3069   
Type: Consent Status: Agenda Ready
File created: 10/28/2026 In control: City Council
On agenda: 12/3/2026 Final action:
Title: Authorize additional contingency funding to the construction contract, for the Zebra Mussels Mitigation Project for Austin Water with Excel Construction Services, LLC, to increase the amount by $210,000, for a revised total contract amount not to exceed $5,150,725. Funding: $210,000 is available in the Capital Budget of Austin Water.
Indexes: District 8
Attachments: 1. Recommendation for Action
Date Action ByActionAction DetailsMeeting Details
No records to display.

Posting Language
Title

Authorize additional contingency funding to the construction contract, for the Zebra Mussels Mitigation Project for Austin Water with Excel Construction Services, LLC, to increase the amount by $210,000, for a revised total contract amount not to exceed $5,150,725. Funding: $210,000 is available in the Capital Budget of Austin Water.

 

Body

Lead Department

Austin Financial Services.

 

Managing Department
Austin Capital Delivery Services.

 

Fiscal Note

Funding is available in the Capital Budget of Austin Water.

 

Procurement Language:

Additional Authorization

 

MBE / WBE:

This contract was awarded in compliance with the City Code Chapter 2-9A (Minority-Owned and Women-Owned Business Enterprises).  Current participation to date is 1.41% MBE and 13.37% WBE.

 

Prior Council Action:

June 16, 2022 - Council approved a contract with Excel Construction Services, LLC. for the Zebra Mussels Mitigation Project.

 

For More Information:

Direct questions regarding this Recommendation for Council Action to the Austin Financial Services - Central Procurement at: FSDCentralProcurementRCAs@austintexas.gov or 512-974-2500.

 

Additional Backup Information:

In 2017, Texas Parks and Wildlife detected zebra mussels in several locations in Lake Austin, and zebra mussels have since been confirmed growing on raw water intake infrastructure at the Davis Water Treatment Plant (WTP), Handcox WTP, and Ullrich WTP. Adult zebra mussels can attach to submerged piping and mechanical equipment, clogging small valves and pipelines, reducing capacity of pipelines, and attaching to pumps which can result in pump failure.

 

Austin Water currently uses copper sulfate treatment systems to control zebra mussel growth in the raw water systems at its water treatment plants. This project will replace these systems with a copper ion generation (CIG) system. CIG is an electrolysis process that produces copper ions without the need of chemical storage and feed systems. CIG systems allow copper to be introduced at the raw water pumps, providing protection to downstream infrastructure and preventing zebra mussel growth within piping and equipment that cannot be accessed by divers. 

 

Austin operates three water treatment plants that supply drinking water to the Austin area. Handcox WTP was built in 2014 and has a current rated capacity of 50 million gallons per day (MGD). Davis WTP was built in 1954 and has been expanded and upgraded to a current capacity of 118 MGD. Ullrich WTP was built in 1969 and has been expanded and upgraded to a current capacity of 167 MGD.  Two CIG vendor systems were selected for installation at the three water treatment plants: ONG was selected for Ullrich and Davis WTPs and Macrotech was selected for the Handcox WTP.

 

The additional contingency funding requested is for costs associated with modifications necessary for the CIG systems to consistently achieve a copper concentration of 10-15 parts per billion. These modifications include upgrading the power supply to 480 volts and adding copper anodes and will also eliminate the need for brine in system operations, reducing long-term operation and maintenance costs.

 

This construction contract is used by Austin Water to complete the CIG system modifications. The current contract authorization has been fully allocated, and any delay in approving the additional contingency funding could affect Austin Water's ability to complete the needed work and respond timely to failures at these critical water treatment facilities. Approval of the requested contingency funding will allow Austin Water to complete the CIG system modifications required to meet the contract performance standard and close out the construction contract. By authorizing the additional contingency funding, Council is authorizing any change orders within the contingency amount.

 

This project is located within zip code 78746 (District 8).

 

 

 

AUTHORIZATION HISTORY

AMOUNT

DATE

DESCRIPTION

$4,435,204.00

06/16/2022

(Council) - Constructions services for Zebra Mussels Mitigation for Davis, Ullrich and Handcox WTPs

$443,520.40

06/16/2022

(Council) - 10% Contingency

$62,000

06/16/2022

(Administrative Authority)

$210,000.00

12/3/2026

Proposed (Council) - Additional Contingency

$5,150,724.40

Total Contract Authorization

 

 

CONTRACT HISTORY

AMOUNT

DATE

DESCRIPTION (CO%/CUMULATIVE CO%)

$4,435,204.00

07/19/2022

Description of awarded service

$8,195.00

01/26/2023

CO 01 - Price increase for Schedule 80 PVC from Schedule 40 (0.18%/0.18%)

$1,790.00

04/27/2023

CO 02 - Equipment costs and labor for four (4) additional isolation valves to be installed on the ionized water lines for the CIG System (0.04%/0.23%)

$3,818.00

05/02/2023

CO 03 - Stand by Time for Divers due to Austin Water Schedule change. (0.09%/0.31%)

$42,150.00

09/15/2023

CO 04 -Ullrich WTP Relocation of the CIG equipment pad and the adjacent 3” PVC and drain lines, and additional power for Ullrich and Davis (0.95%/1.26%)

$47,907.00

01/08/2024

CO 05 - Davis WTP CIG Control Panel and Ullrich WTP 1" Drain Valve (1.08%/2.34%)

$282,150.00

03/28/2024

CO 06 - Davis WTP Booster Pump System (6.36%/8.70%)

$61,187.00

08/02/2024

CO 07 - Ullrich and Davis WTP Brine Tank Containment Tank and heat trace (1.38%/10.08%)

$0.00

10/17/2024

CO 08 - No cost change order for Handcox WTP FAT Travel allowance (0.00%/10.08%)

$0.00

12/13/2024

CO 09 - No cost change order for Handcox WTP FAT Travel allowance (0.00%/10.08%)

$4,399.00

03/25/2025

CO 10 - Relocation of 2" ionized feed valve and addition of ARV drains (0.10%/10.18%)

$0.00

08/08/2025

CO 11 - Additional days due to supplier delays, no additional costs (0.10%/10.18%)

$0.00

08/29/2025

CO 12 -Ullrich WTP FAT Travel allowance (0.10%/10.18%)

$15,750.00

11/27/2025

CO 13 - Ullrich PRV Relocation and JBoxes (0.36%/10.54%)

$0.00

01/21/2026

CO 14 - Davis WTP FAT Travel allowance (0.36%/10.54%)

$210,000

Proposed

Council - CO #15- Contingency for equipment modifications Ullrich and Davis WTP (4.73%/15.27%)

$5,112,471.00

Total Contract History

.