Legislation Details

File #: 26-3068   
Type: Consent Status: Agenda Ready
File created: 10/28/2026 In control: City Council
On agenda: 11/19/2026 Final action:
Title: Authorize an amendment to the contract for engineering services for the Hornsby Bend Biosolids Management Plant Headworks Improvements Project for Austin Water with STV Incorporated, in the amount of $3,213,452, for a revised total contract amount not to exceed $6,269,562. Funding: $3,213,452 is available in the Capital Budget of Austin Water.
Attachments: 1. Recommendation for Action
Date Action ByActionAction DetailsMeeting Details
No records to display.

Posting Language
Title

Authorize an amendment to the contract for engineering services for the Hornsby Bend Biosolids Management Plant Headworks Improvements Project for Austin Water with STV Incorporated, in the amount of $3,213,452, for a revised total contract amount not to exceed $6,269,562.  Funding: $3,213,452 is available in the Capital Budget of Austin Water.

 

Body

Lead Department

Austin Financial Services.

 

Managing Department
Austin Capital Delivery Services.

 

Fiscal Note

Funding is available in the Capital Budget of Austin Water.

 

Procurement Language:

Contract Amendment.

 

MBE / WBE:

This contract will be awarded in compliance with City Code 2-9A (Minority-Owned and Women-Owned Business Enterprise Procurement Program). Current participation to date is 19.79% MBE and 14.21% WBE.

 

Prior Council Action:

6/1/2023 - Council approved a professional service agreement with CP&Y Inc / STV Infrastructure for Hornsby Bend Biosolids Management Plant Headworks.

 

10/17/2019 - Council approved a professional service agreement with CP&Y Inc for the Hornsby Bend Biosolids Management Plant Headworks Project.

 

For More Information:

Direct questions regarding this Recommendation for Council Action to the Austin Financial Services - Central Procurement at: FSDCentralProcurementRCAs@austintexas.gov or 512-974-2500.

 

Council Committee, Boards and Commission Action:

November 10, 2026 - To be reviewed by the Water and Wastewater Commission.

 

May 10, 2023 - Recommended by the Water and Wastewater Commission on a 6-0 vote with Vice Chair Musgrove’s motion, Commissioner Angoori’s second and five vacancies.

 

October 9, 2019 - Recommended by the Water & Wastewater Commission on a 7-0-2-2 vote with Commissioner Moriarty’s motion, Commissioner Castleberry’s second, Commissioners Penn and Turrieta recused and Commissioners Parton and Schmitt absent.

 

Additional Backup Information:

The Hornsby Bend Biosolids Management Plant (HBBMP) and Bird Observatory is located on a 1200-acre site that stretches along 3.5 miles of the Colorado River, approximately eight miles east of downtown Austin.  The plant has grown into a nationally recognized and award-winning biosolids recycling facility and previously the recipient of a first-place award by the U.S. Environmental Protection Agency (EPA) for its recycling program.

 

The HBBMP headworks contains a screening process, which is the first step in the biosolid’s treatment process. The existing headworks equipment has limited capacity and has exceeded its useful service life. The purpose of this project is to replace the headworks facility entirely and add a new sludge receiving station.  The new headworks will increase screening capacity, provide odor control, replace the existing screens which are beyond their useful life and the critical electrical infrastructure.

 

This amendment is for additional engineering consulting services for the construction and warranty phases, and a design for a backup thickening system to replace an existing system located in the headworks improvement project’s limits of construction. 

 

There will be no impact to the public.  All work will be performed on property that is not accessible to the public.

 

Any delay in execution could have impacts on Austin Water’s ability to process/treat biosolids pumped to the HBBMP from Austin’s main wastewater treatment plants.

 

AUTHORIZATION HISTORY

 

AMOUNT

DATE

DESCRIPTION

$750,000.00

10/17/2019

(Council) - Professional Engineering Services

$2,075,500.00

06/01/2023

(Council) - Professional Engineering Services

$3,213,451.11

12/03/2026

Proposed (Council) - Professional Engineering Services

$6,038,951.11

Total Contract Authorization

 

CONTRACT HISTORY

 

AMOUNT

DATE

DESCRIPTION

$749,853.43

08/10/2020

Professional Engineering Services Preliminary Phase

$1,873,596.70

07/07/2023

SA # 1 - Professional Engineering Services Design and Bid Phases

$117,332.36

01/27/2025

SA # 2 - Professional Engineering Services - Additional Services

$3,213,451.11

12/03/2026

SA # 3 - Professional Engineering Services Construction Phase

$5,954,233.60

Total Contract History

.