Posting Language
Title
Authorize an amendment to the City's cost participation with the developer United Properties Development, LLC to increase the City's share of the cost to design and construct oversized wastewater interceptors by $4,422,750, for a total amount not to exceed $9,500,000, related to Service Extension Request No. 5132R which will provide wastewater service to a proposed mixed-use development located at East Howard Lane and SH 130. Funding: $9,500,000 is available in the Fiscal Year 2025-2026 Capital Budget of Austin Water.
De
Lead Department
Austin Water.
Fiscal Note
Funding is available in the Fiscal Year 2025-2026 Capital Budget of Austin Water.
Prior Council Action:
April 18, 2024 - Council authorized a cost reimbursement agreement for an amount not to exceed $5,077,250.
For More Information:
Inquiries should be directed to Vicky Addie, Program Coordinator, 512-972-0332, or Vicky.Addie@austintexas.gov.
Council Committee, Boards and Commission Action:
March 11, 2026 - Recommended for approval by the Water and Wastewater Commission on a 6-0 vote with three Commissioners absent and one Commissioner off the dais.
Additional Backup Information:
The Howard Lane Industrial - West project consists of approximately 94 acres of land located north and south of East Howard Lane and west of SH 130 (Property). The Property is located entirely within the City's two-mile extra-territorial jurisdiction, Impact Fee Boundary, Austin Water's service area, the Desired Development Zone, and the Gilleland Watershed. A map of the Property is attached.
United Properties Development, LLC (Applicant) is proposing to develop approximately 398,000 square feet of industrial warehouse space, 8,150 square feet of retail space, 7,700 square feet of restaurant space, and 710 multifamily units. Service Extension Request (SER) No. 5132R was submitted and approved to extend City wastewater service to the Property. Manville Water Supply Corporation will provide retail wat...
Click here for full text