Title: Authorize change order five to the construction contract for the Hyde Park Water and Wastewater Pipeline Renewal Project for Austin Water with Santa Clara Construction Ltd., in the amount of $831,153, for a total contract amount not to exceed $9,392,249. Funding: $831,153 is available in the Capital Budget of Austin Water.
Indexes: District 9
Attachments: 1. Recommendation for Action, 2. WWWC Voting Outcome
Date Action ByActionAction DetailsMeeting Details
No records to display.
Posting Language
Title
Authorize change order five to the construction contract for the Hyde Park Water and Wastewater Pipeline Renewal Project for Austin Water with Santa Clara Construction Ltd., in the amount of $831,153, for a total contract amount not to exceed $9,392,249. Funding: $831,153 is available in the Capital Budget of Austin Water.

Body
Lead Department
Austin Financial Services.

Managing Department
Austin Capital Delivery Services.

Fiscal Note
Funding is available in the Capital Budget of Austin Water.

Procurement Language:
Change Order.

MBE / WBE:
This contract was awarded in compliance with the City Code 2-9A (Minority-Owned and Women-Owned Business Enterprise Procurement Program). Current participation to date is 62.20% MBE and 0.95% WBE.

Prior Council Action:
December 9, 2021 - Council approved a contract with Santa Clara Construction Ltd. for the Hyde Park Water and Wastewater Pipeline Renewal Project.

For More Information:
Direct questions regarding this Recommendation for Council Action to Austin Financial Services - Central Procurement at FSDCentralProcurementRCAs@austintexas.gov or 512-974-2500.

Council Committee, Boards and Commission Action:
May 20, 2026 - To be reviewed by Water and Wastewater Commission.

Additional Backup Information:
The Hyde Park Water and Wastewater Pipeline Renewal project is part of the Renewing Austin Program. The Renewing Austin Program is an ongoing effort to replace, and upgrade deteriorated and aging water mains with a documented history of multiple breaks, that are in poor condition, and that impact service delivery. In addition, the program coordinates and includes wastewater lines and other needed improvements by other departments within the project area.

During construction, Austin Water requested additional water utility infrastructure to be added to the project. Located along W. 46th St., between Avenue G and Avenue F, the added construction included a total of approximately 340 linear feet...