Title: Authorize an amendment to the contract for engineering services for the Boggy Creek Lift Station Force Main Extension Project for Capital Delivery Services with AECOM Technical Services, Inc., in the amount of $600,000, for a revised total contract amount not to exceed $2,200,000. Funding: $600,000 is available in the Capital Budget of Austin Water.
Attachments: 1. MWBE Summary, 2. Auth History, 3. Recommendation for Action
Date Action ByActionAction DetailsMeeting Details
No records to display.
Posting Language
Title
Authorize an amendment to the contract for engineering services for the Boggy Creek Lift Station Force Main Extension Project for Capital Delivery Services with AECOM Technical Services, Inc., in the amount of $600,000, for a revised total contract amount not to exceed $2,200,000. Funding: $600,000 is available in the Capital Budget of Austin Water.

Body
Lead Department
Financial Services Department.

Managing Department
Capital Delivery Services.

Amount and Source of Funding
Funding is available in the Capital Budget of Austin Water.

Purchasing Language:
Contract Amendment.

MBE / WBE:
This contract was awarded in compliance with City Code 2-9A (Minority-Owned and Women-Owned Business Enterprise Procurement Program). Current participation to date is 15.63% MBE and 19.65% WBE.

Prior Council Action:
December 5, 2019 - Council approved a contract for engineering services with AECOM Technical Services, Inc., for the Boggy Creek Lift Station Force Main Extension Project.

For More Information:
Direct questions regarding this Recommendation for Council Action to the Financial Services Department - Central Procurement at: FSDCentralProcurementRCAs@austintexas.gov or 512-974-2500.

Council Committee, Boards and Commission Action:
May 21, 2025 - Recommended by the Water and Wastewater Commission on a vote of 7-0 with Commissioner Penn recusing and three vacancies.

November 13, 2019 - Recommended by the Water and Wastewater Commission on a 7-0-1-3 vote with Commissioner Penn recusing, Commissioner Ho off the dais, and Commissioners Schmitt and Williams absent.

Additional Backup Information:
The Boggy Creek Lift Station Force Main Extension will construct a new wastewater line to extend the existing discharge force main from Boggy Creek Lift Station to tie directly into the Govalle Tunnel at the Lockheed Shaft.

The comprehensive work includes approximately 9,300 linear feet of a new 36-inch wastewater line, abandonment of two aging drain...