Posting Language
Title
Authorize a contract for construction services for the West Bouldin Creek - Del Curto Storm Drain Improvements and SOLA-C3.005 Intersection Improvements Bluebonnet Lane and Del Curto Road project with Santa Clara Construction, Ltd., in the amount of $8,781,522, plus a $878,153 contingency, for a total contract amount not to exceed $9,659,674. Funding: $9,080,093 is available in the Capital Budget of the Watershed Protection Department, $579,581 is available in the Capital Budget of the Transportation and Public Works Department.
Body
Lead Department
Financial Services Department.
Managing Department
Watershed Protection Department.
Amount and Source of Funding
Funding in the amount of $9,080,093 is available in the Capital Budget of the Watershed Protection Department.
Funding in the amount of $579,581 is available in the Capital Budget of the Transportation and Public Works Department.
Purchasing Language:
The Financial Services Department issued an Invitation for Bids solicitation IFB 6100 CLMC1076 for these goods and services. The solicitation was issued on June 2, 2025, and closed on July 10, 2025.
Of the eight offers received, the recommended contractor submitted the lowest responsive offer. A complete solicitation package, including a tabulation of the bids received, is available for viewing on the City's website. This information can currently be found at https://financeonline.austintexas.gov/afo/account_services/solicitation/solicitation_details.cfm?sid=141292
.
MBE/WBE:
This contract will be awarded in compliance with the City Code Chapter 2-9A (Minority-Owned and Women-Owned Business Enterprise Procurement Program) by meeting the goals with 74.38% MBE and 1.51% WBE participation.
For More Information:
Direct questions regarding this Recommendation for Council Action to the Financial Services Department - Central Procurement at FSDCentralProcurementRCAs@austintexas.gov or 512-974-2500. Respondents to the solicitation and...
Click here for full text