Authorize a contract for construction services for the Lady Bird Lake Bore for Pedernales Reconductor project for Austin Energy with Austin Underground, Inc., in the amount of $2,733,915, plus a $273,391 contingency, for a total contract amount not to exceed $3,007,306. Funding: $3,007,306 is available in the Capital Budget of Austin Energy.
Body
Lead Department
Austin Financial Services.
Managing Department
Austin Energy.
Fiscal Note
Funding is available in the Capital Budget of Austin Energy.
Procurement Language:
Austin Financial Services issued an Invitation for Bids solicitation IFB 6100 CLMC1056 for these services. The solicitation was issued on May 13, 2024, and closed on October 2, 2025. Of the five bids received, the bid submitted by the recommended contractor was the lowest responsive bid. A complete solicitation package, including a tabulation of the bids received, is available for
viewing on the City's website. This information can currently be found at https://financeonline.austintexas.gov/afo/account_services/solicitation/solicitation_details.cfm?sid=141090.
MBE / WBE:
This contract will be awarded in compliance with City Code Chapter 2-9A (Minority-Owned and Women- Owned Business Enterprise Procurement Program) by meeting the goals with 72.31% MBE and 0.15% WBE participation.
For More Information:
Direct questions regarding this Recommendation for Council Action to Austin Financial Services - Central Procurement at FSDCentralProcurementRCAs@austintexas.gov or 512-974-2500. Respondents to the solicitation and their Agents should direct all questions to the Authorized Contact Person identified in the solicitation.
Council Committee, Boards and Commission Action:
March 9, 2026 - Recommended by the Electric Utility Commission on an 11-0 vote.
Additional Backup Information:
The Lady Bird Lake Bore for Pedernales Reconductor project is located East of Interstate 35 and crosses under Lady Bird Lake with the entry/exit poi...