Posting LanguageTitle
Approve a settlement to the claim from Jay-Reese Contractors, Inc. related to the construction contract for the Rainey Street Gas-Insulated Switchgear Substation project.
De
Lead Department
Law Department.
Fiscal Note
Funding is available in the Fiscal Year 2023-2024 Austin Energy Approved C.I.P. Budget, in the Rainey Steet Gas-Insulated Switchgear Substation Project’s Distribution Substation Account.
For More Information:
Jake Petry, Assistant City Attorney, (512) 974-2918.
Additional Backup Information:
This is a contract claim related to the construction of Austin Energy’s Rainey Street Gas-Insulated Switchgear Substation located at 806 1/2 Lambie Avenue.