File #: 26-2784   
Type: Consent Status: Agenda Ready
File created: 12/29/2025 In control: City Council
On agenda: 1/22/2026 Final action:
Title: Authorize an amendment to the contract for the Airport Expansion and Development Program Utility Infrastructure Campus Wide Project for Austin Aviation with HDR Engineering, Inc., to increase the amount by $18,000,000, for a revised total contract amount not to exceed $28,000,000. Funding: $18,000,000 is available in the Capital Budget of Austin Aviation.
Indexes: District 2
Attachments: 1. Recommendation for Action
Date Action ByActionAction DetailsMeeting Details
No records to display.
Posting Language
Title
Authorize an amendment to the contract for the Airport Expansion and Development Program Utility Infrastructure Campus Wide Project for Austin Aviation with HDR Engineering, Inc., to increase the amount by $18,000,000, for a revised total contract amount not to exceed $28,000,000. Funding: $18,000,000 is available in the Capital Budget of Austin Aviation.

Body
Lead Department
Austin Financial Services.

Managing Department
Austin Capital Delivery Services.

Fiscal Note
Funding is available in the Capital Budget of Austin Aviation.

Procurement Language:
Contract Amendment.

MBE / WBE:
This contract was previously awarded in compliance with City Code Chapter 2-9A (Minority-Owned and Women-Owned Business Enterprise Procurement Program). Per 49 Code of Federal Regulations Part 26 Disadvantaged Business Enterprise (DBE) Program, DBE participation may not be considered.

Prior Council Action:
November 30, 2023 - Council approved Construction Manager-at-Risk methodology.

May 30, 2024 - Council approved a professional services agreement with HDR Engineering, Inc. for engineering design services for the Airport Expansion and Development Program Utility Infrastructure Campus Wide project.

For More Information:
Direct questions regarding this Recommendation for Council Action to the Financial Services Department - Central Procurement at FSDCentralProcurementRCAs@austintexas.gov or 512-974-2500.

Council Committee, Boards and Commission Action:
January 14, 2026 - To be reviewed by the Airport Advisory Commission.

Additional Backup Information:
The new Concourse B and the Arrivals and Departures Hall have increased in size and complexity to better meet airline operational needs and accommodate higher passenger demand and project growth. A critical enabling project for delivering these expanded facilities is the Utility Infrastructure Campus-Wide (UICW) Project.

The UICW project focuses on upgrading and adding essential utility systems, incl...