Posting Language
Title
Authorize a contract for purchase of one complete, spare rotor assembly for Austin Energy with WEG Electric Corp., in an amount not to exceed $1,750,000. Funding: $550,000 is available in the Capital Budget. $1,200,000 is available in the Operating Budget of Austin Energy.
Body
Lead Department
Austin Financial Services.
Client Department(s)
Austin Energy.
Fiscal Note
Funding in the amount of $550,000 is available in the Capital Budget.
Funding in the amount of $1,200,000 is available in the Fiscal Year 2025-2026 Operating Budget of Austin Energy.
Procurement Language:
Sole Source.
MBE/WBE:
Sole source contracts are exempt from the City Code Chapter 2-9B (Minority-Owned and Women-Owned Business Enterprise Procurement Program); therefore, no subcontracting goals were established.
For More Information:
Direct questions regarding this Recommendation for Council Action to Austin Financial Services – Central Procurement at: FSDCentralProcurementRCAs@austintexas.gov or 512-974-2500.
Council Committee, Boards and Commission Action:
September 14, 2026 - To be reviewed by the Electric Utility Commission.
Additional Backup Information:
This contract provides for the purchase of one complete, spare rotor assembly. Although Austin Energy is committed to using these units as little as possible, a spare rotor assembly will enable Austin Energy to increase reliability and availability during critical periods of peak power demand.
The authorized repair facility for the Decker Creek Power Station, Pratt & Whitney FT4 generation units is in Massachusetts and the process to ship, repair and return a rotor takes five months at minimum. Maintaining a fully assembled spare rotor will minimize repair downtime, maintain black-start capability, and strengthen reliability.
WEG Electric Machinery is the original equipment manufacturer of the Pratt & Whitney FT4 and is the sole source of proprietary drawings, material specifications, dimensional toleranc...